Desarrollo de un modelo para el seguimiento y control económico y temporal durante la fase de ejecución en la obra pública. Integration of information for advanced detection of cost overruns-IMADO

The primary objective of this research is to modify the models regularly used to record and monitor the implementation costs of public works projects from the perspective of the promotor, the project directors or the project managers. This is done with a structure similar to the traditional system of meticulously recording project costs to obtain additional trustworthy and accurate information about current and future economic deviations that may occur during project implementation and about the probable liquidation and closing horizon of the project. That is possible if the economic information generated during the project implementation, which current cost control models do not incorporate until its implementation is certified, are incorporated into the structures of existing models for the control and monitoring of implementation costs. The sub-objectives of this research include applying this new technology and the new model to improve permanent control of the amount of economic deviations sustained during project implementation, identify the causes of deviation, graphically and analytically represent the economic behaviour, comply with the deadline for implementing the project and incorporate dashboards into periodical project reports

El principal objectiu d’aquesta investigació és modificar els models que s’utilitzen habitualment per registrar i monitoritzar els costos durant el procés d’execució d’obra des de la perspectiva del promotor públic, de la direcció facultativa o la dels gestors del projecte, a fi que amb una estructura de registre similar i respectuosa amb la informació que s’obté del tradicional sistema de registre de control de costos d’obra, sigui possible obtenir addicionalment informació fiable i veraç sobre les desviacions econòmiques presents i futures que poden esdevenir durant l’execució, així com sobre l’horitzó probable de liquidació i tancament de l’obra, d’acord amb la informació disponible. Això és possible si s’incorpora a les estructures dels models actuals de control i seguiment de costos d’execució, la informació d’índole econòmic que es genera durant el procés de realització de l’obra i que no contemplen els actuals models de control de costos fins al moment concret de l’acreditació de la seva execució a obra. Paral·lelament, aquesta investigació es marca com subobjectius la possibilitat de millorar, mitjançant la proposta d’aquesta nova metodologia i l’aplicació del nou model, el control permanent del volum total de les desviacions econòmiques que suporta l’execució d’obra, la possibilitat d’assignació de causes de desviació, la representació gràfica i analítica del comportament econòmic i de compliment de termini de l’execució d’obra, així com la incorporació de quadres de comandament als informes periòdics d’obra

Universitat de Girona

Director: Ribera Roget, Albert
Ciurana, Quim de
Altres contribucions: Universitat de Girona. Departament d’Enginyeria Mecànica i de la Construcció Industrial
Autor: Gifra Bassó, Ester
Data: 5 març 2018
Resum: The primary objective of this research is to modify the models regularly used to record and monitor the implementation costs of public works projects from the perspective of the promotor, the project directors or the project managers. This is done with a structure similar to the traditional system of meticulously recording project costs to obtain additional trustworthy and accurate information about current and future economic deviations that may occur during project implementation and about the probable liquidation and closing horizon of the project. That is possible if the economic information generated during the project implementation, which current cost control models do not incorporate until its implementation is certified, are incorporated into the structures of existing models for the control and monitoring of implementation costs. The sub-objectives of this research include applying this new technology and the new model to improve permanent control of the amount of economic deviations sustained during project implementation, identify the causes of deviation, graphically and analytically represent the economic behaviour, comply with the deadline for implementing the project and incorporate dashboards into periodical project reports
El principal objectiu d’aquesta investigació és modificar els models que s’utilitzen habitualment per registrar i monitoritzar els costos durant el procés d’execució d’obra des de la perspectiva del promotor públic, de la direcció facultativa o la dels gestors del projecte, a fi que amb una estructura de registre similar i respectuosa amb la informació que s’obté del tradicional sistema de registre de control de costos d’obra, sigui possible obtenir addicionalment informació fiable i veraç sobre les desviacions econòmiques presents i futures que poden esdevenir durant l’execució, així com sobre l’horitzó probable de liquidació i tancament de l’obra, d’acord amb la informació disponible. Això és possible si s’incorpora a les estructures dels models actuals de control i seguiment de costos d’execució, la informació d’índole econòmic que es genera durant el procés de realització de l’obra i que no contemplen els actuals models de control de costos fins al moment concret de l’acreditació de la seva execució a obra. Paral·lelament, aquesta investigació es marca com subobjectius la possibilitat de millorar, mitjançant la proposta d’aquesta nova metodologia i l’aplicació del nou model, el control permanent del volum total de les desviacions econòmiques que suporta l’execució d’obra, la possibilitat d’assignació de causes de desviació, la representació gràfica i analítica del comportament econòmic i de compliment de termini de l’execució d’obra, així com la incorporació de quadres de comandament als informes periòdics d’obra
Format: application/pdf
Altres identificadors: http://hdl.handle.net/10803/550975
Accés al document: http://hdl.handle.net/10256/15482
Llenguatge: spa
Editor: Universitat de Girona
Drets: L’accés als continguts d’aquesta tesi queda condicionat a l’acceptació de les condicions d’ús establertes per la següent llicència Creative Commons: http://creativecommons.org/licenses/by/4.0/
Matèria: Construcción
Construcció
Construction
Obra pública
Public works
Control de costes
Cost control
Control de costos
Sobrecosto
Sobrecost
Cost overrun
Costo estimado
Cost estimat
Estimated cost
33 - Economia
624 - Enginyeria civil i de la construcció en general
Títol: Desarrollo de un modelo para el seguimiento y control económico y temporal durante la fase de ejecución en la obra pública. Integration of information for advanced detection of cost overruns-IMADO
Tipus: info:eu-repo/semantics/doctoralThesis